Guidelines Project Risk Management
SW/G09/1.0.0 Internal Page 1 of 12

  Uncontrolled copied/ printed
Project Risk Checklist
Instructions for using this document
Section   I   of   this   template   is   used   to   determine   whether   there   are   inherent   risks   to   your   project.   The   results   should   be   used   as   guidelines,  since   there   will   be   other   factors   that   may   lower   or   raise   the   risk   level.   For   instance,   you   may   have   a   large   project,   which   implies   higher   risk.  This   risk   could   be   reduced   if   you   also   have   an   experienced   project   manager.   Depending   on   where   your   project   characteristics   fall,   you   can  evaluate   whether   your   risk   is   high,   medium,   or   low.   (Medium   risks   fall   in   between   the   extremes.)   If   your   project   has   many   high-risk  characteristics, it does not mean you will not be successful. However, it does mean that you should put a plan place to manage the risk.
This   checklist   can   be   especially   valuable   if   your   organization   customizes   the   specific   risk   characteristics   and   risk   criteria   that   apply   to   your  company.   For   instance,   you   may   find   that   in   your   organization,   a   project   of   less   than   5,000   hours   is   considered   low-risk,   while   one   that   is  20,000 hours more is high-risk.
When   you   have   completed   the   checklist,   look   at   all   of   the   high-risk   items   and   refer   to   Section   II   of   this   template.   In   this   section,   you   will   see  each   high-risk   factor   and   examples   of   problems   you   may   encounter.   For   each   high-risk   factor,   create   a   plan   to   ensure   that   the   risk   is  mitigated   and   does   not   occur.   The   second   column   of   Section   II   shows   examples   of   activities   that   can   be   added   to   the   risk   plan   to   help  mitigate the risk.
After   the   high-risk   factors   have   been   evaluated,   look   at   the   medium-level   risks   to   determine   if   the   impact   is   severe   enough   that   they   should  have   a   risk   mitigation   plan   created   for   them   as   well.   If   so,   create   a   risk   plan   for   them.   Then   look   at   any   low-risk   items   and   see   whether   they  should   be   listed   as   assumptions.   In   this   way,   you   recognize   that   there   is   a   potential   for   problems,   but   because   the   risk   is   low,   you   are  “assuming”   that   the   condition   will   not   occur.   The   activities   associated   with   managing   the   various   risks   should   then   be   moved   to   your   project  work plan.
This shall be used the planning stage of project i.e. of Project management plan. The risks the  project shall identified and the appropriate mitigation and contingency plans identified under the sec 13 of PMP.
Guidelines Project Risk Management
SW/G09/1.0.0 Internal Page 2 of 12

  Uncontrolled if copied/ printed
Section I - Project Risk factors:


Characteristics

Low risk

Medium  risk

High risk
The business benefit of project is:
-Well defined
-
--Poorly defined
The scope of project is:
-Well defined
-
--Poorly defined
The project sponsor is:
-Identified, committed, and enthusiastic
-
-- identified or enthusiastic
The business customer level is:
-Passionate and enthusiastic
-
--Passive and hard to engage
The project manager has:
-Similar experience on multiple projects
-
--Little experience on similar projects
The project team is:
-Located together
-
--Dispersed at multiple sites
Project management processes and procedures  are:
--Familiar will be utilized
-
--Not familiar will not be utilized
business requirements of the project are:
--Understood and straightforward
-
--Very vague or very complex
The system availability requirements include:
-- Windows of availability and downtime
-
-- Availability on a 24/7 basis
The technical requirements are:
--Similar to others in the company
-
--New complex
requirements are:
--Simple
-
--Complex
The of locations deploy to is:
--One
-
-- than four
The number of system interfaces are:
--One or none
-
--More than five
The number of organizations this will affect is:
--One or two
-
--More five
total estimated effort are:
--Less 1,000
-
--Greater 5,000
The total estimated project duration is:
-- Less three months
-
-- Longer than one year
The subject matter is:
-- Well known by the project team
-
-- well known by the project team
The project is dependent on:
--Zero or one outside project or team
-
-- or more outside teams or  projects
Business processes, procedures, policies  require:
--Little or no change
-
-- Substantial change



















































































Guidelines for Project Risk Management
SW/G09/1.0.0 Internal Page 3 of 12

  Uncontrolled copied/ printed
Changes to the organizational structure require:
-- or no change
-
-- Substantial change
The technology being utilized consists of:
-- Existing software, hardware, languages,  databases, and tools
-
-- New software, hardware, languages,  databases, or tools (or new releases)
The quality of current data is:
-- Well defined and simple to convert
-
--Poor or complex to convert
If a package implementation:
-- No (or minimal) is needed
-- The or release is stable
--The vendor is familiar in this market
-
-
-
-- Heavy customization is needed
--The product or release new to the  market
-- The vendor is new to this market



















Section II—Risk management strategy tables


High-risk factors/
Potential problems 

Risk management activities
business benefit of the project is defined
• Project   is   in   jeopardy   of   being   placed   on   hold   or   cancelled   if  higher value work is identified
• to get resources required
• Hard to evaluate the value of the project to the organization
• Hard define scope changes in terms of cost/benefit
• Hard   to   know   if   business   value   was   achieved   when   project   is  complete
• Try to get business customer to quantify the overall business value of the project
• Look at the major requirements try to quantify the value of the various deliverables
• Document the intangible benefit that the project will achieve
• Review prior similar projects see how the benefits were quantified
• Don’t start the project while business is undefined







Guidelines for Project Risk Management
SW/G09/1.0.0 Internal 4 of 12

  Uncontrolled if copied/ printed
scope of the project poorly defined
• Hard provide sound estimates
• May spend time and cost on areas out of scope
• Hard to gather concise requirement
• Difficult to write project definition and work plan
• Hard to invoke scope-change procedures
• Project deliverables are defined
• Focus on firming up scope in the planning process
• Define   various   components   of   scope,   such   as   what   organizations   are   affected,   what  deliverables are expected, what type of information is required
• Clearly is out scope for the project
• Begin   to   define   business   requirements   at   a   high   level   and   then   work   upward   to   define  scope
• Ask project sponsor to decision on conflicting scope statements
• Document all scope assumptions providing of work, cost, or duration
• Use pictures or diagrams to communicate and options
• Establish firm scope-change procedures up front
• Ensure   the   project   definition   and   business   requirements   are   formally   approved   and   signed  off on
• Distribute statements all stakeholders confirmation
• Do not begin project until scope is clear
The sponsor is not identified or not enthusiastic
• Project may not the resources it needs
• Project may not have the long-term commitment needed
• Political battles may delay the project
• Issues   and   change   requests   may   not   be   resolved   in   a   timely  manner
• Establish a strong steering to help guide the project
• Establish a process for resolving disputes between organizations
• Try to identify a different sponsor
• Ask the sponsor delegate full authority to another person who can act on behalf
• Don’t start the project
Customer level is passive/hard engage
• May point out low confidence in the business value
• Harder to get customer time and resources needed
• Harder to gather business requirements
• Customers may undermine or work against the project
• Create   an   aggressive   communication   plan   to   keep   customers   engaged   and   communicate  the business benefit
• Create user group to surface concerns and enthusiasm
• Ask for customer participation in planning and requirements gathering
• Ask for help from the sponsor to generate excitement
• Look for to project fun settings and contexts
• Be proactive in gaining commitments for customer resources when you need them
• Don’t project
Project management experience light
• May take longer define the project and work plan
• May   make   more   mistakes   in   judgment,   causing   rework   and  project delays
• More difficulty organizing and managing a complex project
• May   not   be   familiar   with   sound   project   management  practices
• May not know when to call for help
• Provide up-front project management training
• Designate a more senior to coach and mentor the project manager
• Break the project into smaller pieces that are to manage
• Put a strong quality-assurance process in place ensure the is on the right track
• Make sure the major deliverables are approved
• Utilize strong team leaders and team members to bring additional experience bear











Guidelines for Project Risk Management
SW/G09/1.0.0 Internal 5 of 12

  Uncontrolled if copied/ printed
Project is in locations
• Harder communicate effectively
• Less interaction and cohesion
• Harder to build relationship with the entire team
• Some members may feel isolated and not a part of the team
• Technology problems may result in productivity decrease
• Try to get the team one location, at least for the length of the project
• an aggressive communication plan to ensure the team communicates effectively
• Hold regular meetings where the entire team meets face-to-face
• team- activities the entire team meets face-to-face
• Have backup methods to if the primary technology fails
• Maintain contact by phone with remote team members
• Create   a   central   repository   to   hold   the   project   documentation   that   all   team   members   can  access
Project   management   processes   are   unfamiliar   or   will   not  be used
• Team   may   have   a   difficult   time   understanding   how   to   raise  issues, scope changes, and risks
• Project   may   get   out   of   control   as   the   internal   processes  become more complex and harder to manage
• Communication will tend to poorer
• Project deliverables might be completed in different formats
• Issues   may   not   be   addressed   in   a   timely   manner,   scope  changes   may   be   adopted   without   thought   of   impact   to   the  project,   risks   may   be   ignored,   and   quality   may   be  compromised
• Chance   that   the   project   may   be   in   trouble   before   it   is  recognized
• Provide   training   to   the   project   manager   and   project   team   on   sound   project   management  processes and procedures
• Assign an experienced project management coach or mentor to the project
• Break   the   project   into   smaller   pieces   that   can   be   managed   with   less-rigorous   project  management
• Define   and   gain   approval   for   a   set   of   project   management   procedures   before   the   project  starts,   including   issues   management,   change   management,   risk   management,   and   quality  management
• Create   a   solid   communication   plan   to   ensure   everyone   knows   what’s   going   on   and   can  provide feedback
• Solicit input on issues, risk, scope change, and quality concerns on basis
The   business   requirements   of   the   project   are   vague   or  complex
• Difficult to document the requirement properly
• Difficult to use to document the requirements
• Difficult   to   understand   what   the   expectations   of   the   project  are
• Chance   that   the   resulting   solution   will   not   meet   business  need
• May be a sign of a lack of focus the customer
• Use   joint   application   design   (JAD)   session   to   gather   requirements   from   all   stakeholders  together
• Utilize   prototyping   and   iterative   development   techniques   to   assist   users   in   discovering   the  requirements of the new system
• Get access to the sponsor senior management to provide overall guidance
• Provide training to customers on how to think about and express business requirements
• Ensure   that   the   final   business   requirements   are   approved   in   writing   and   that   a   change- management procedure is enforced after that









Guidelines for Project Risk Management
SW/G09/1.0.0 Internal Page 6 of 12

  Uncontrolled if copied/ printed
The system availability requirements 24/7
• Downtime   problems   may   result   in   productivity   decreases   or  of revenue
• Redundancy   may   be   needed,   which   increases   system  complexities
• Newer advanced technology may be required
• More   procedures   and   processes   are   needed   to   maintain   the  system environment
• more time to analysis, design, testing, and overall quality assurance activities
• Focus extra time and energy on technology architecture
• Focus more time and energy on design
• Use industry best practices all technology and process components
• Provide   appropriate   training   to   the   team   so   they   understand   the   24/7   implications   on   the  project
• Determine exactly what portions of the system have a 24/7 requirement
• Look internal experts to overall technical design and architecture
• solid disaster procedures
• Develop a strong partnership with the hardware and software vendors
The technical requirements are new and complex
• May   be   difficult   to   understand   the   requirements   and   the  implications of design decisions
• integration issues between and new technology
• May be difficulty testing the complex technology
• The   more   complex   the   technology,   the   greater   the   risk   that  problems will occur
• Problems   with   incompatible   technologies   may   not   be  uncovered until integration or system testing
• Utilize   system   and   technical   design   documents   to   clearly   lay   out   how   the   technology   fits  together
• Define   the   overall   system   technical   architecture   and   have   it   approved   by   knowledgeable  in your company
• Send the architecture proposal to outside consultants for further feedback and validation
• Create a pilot test or utilize the new technology in a way at first
• Try to substitute more proven and familiar technology in architecture 
• Utilize multiple products from the same vendor to ease integration complexities
• Use   products   that   utilize   open   standards   and   architectures   to   reduce   the   risk   of   integration  problems
The project data requirements complex
• Hard understand the implications of data relates 
• Hard   to   know   if   and   when   all   data   elements   have   been  captured
• More   likely   that   some   data   elements   will   be   discovered  missing until system construction
• Solution   may   have   more   limited   value   if   all   required   data   is  not present
• Solution   will   take   longer   to   analyze,   design,   construct,   and  test
• Utilize an automated tool to capture data elements and the relationships
• Gain agreement on logical design before databases are built
• Gather customer approval for once they are completed
• Utilize   trained   data   architects   to   help   collect   the   data   and   design   what   the   data   structures  should look like









Guidelines for Project Risk Management
SW/G09/1.0.0 Internal Page 7 12

  Uncontrolled if copied/ printed
Many locations to deploy to 
• May be different requirements from the different locations
• May be different procedures, processes, or technology
• May   be   technology   problems   with   tying   all   the   pieces  at each location
• Technology   infrastructure   may   be   different   at   different  locations
• Gather requirements all locations deploy to
• Make   sure   the   sponsor   agrees   with   any   customization   of   process   or   system   based   on  locations
• Implement   at   a   simple   site   first   to   gain   experience   and   modify   implementation   process  before proceeding with all sites
• Make   sure   an   overall   architecture   is   in   place   that   will   flexibly   accommodate   all   locations   and  any communication that take place
• sure the technical infrastructure understood at each location
Many system interfaces 
• Increased of testing
• More reliance other projects or systems
• More chance for incompatibility
• Harder to down problems, errors, and bugs
• Reduce need interfaces when possible
• the of information being passed when possible
• Use as flexible a technology for the interface as (i.e., XML)
• Break the project into smaller subprojects with fewer interfaces to manage
• Work   early   to   set   expectations   regarding   the   need   for   knowledgeable   resources   from   the  other systems
• Test the interfaces as early in the project as possible
• Add extra analysis to ensure the needs of the interfaces are well understood
• Include   the   people   that   support   the   interfaces   in   the   official   communication   and   status  reporting
High number of organizations are affected
• Coordination more complex
• Approvals be more and lengthy
• difficult to reach consensus
• More   people   and   groups   to   involve   in   planning   and  requirements
• Harder   to   know   the   major   stakeholders   of   the   various  organizations 
• Implementation harder and more complex
• Establish a approval process
• Create a steering committee to represent the entire stakeholder community
• Keep the sponsor engaged and ready to intervene in the organizations
• Include   representative   from   each   organization   in   requirements,   quality   assurance,   and  testing
• Include opportunities for people from the various organizations to meet and interact
• Work with the team on adherence to overall project objectives and priorities
• Use consensus-building techniques at all possible









Guidelines for Project Risk Management
SW/G09/1.0.0 Internal Page 8 of 12

  Uncontrolled if copied/ printed
High number of estimated effort hours
• Implication   of   a   high   number   of   effort   hours   is   that   there  are many people and more complexity 
• Harder to communicate effectively with the team
• Bottlenecks occur when decisions are needed quickly
• More chance of people problems
• Increased of turnover
• More to train
• Use a project management tool to utilization
• Have   team   members   utilize   weekly   status   reports   to   report   on   progress   against   their  assigned workplan activities
• Utilize team leaders manage sub teams
• Organize team-building activities build cohesion
• Schedule status meetings keep people of project status
• Utilize structured internal procedures scope, issue, quality, and risk management
• the project into smaller, shorter subprojects 
• Reduce   available   project   work   time   per   person,   per   day   to   recognize   additional   people   and  team- activities
Long estimated project duration
• to manage schedule 
• Easier team and the customer to drift or lose focus
• More   chance   that   project   will   lose   organizational  commitment
• More chance business requirements will change
• More of change in software or hardware versions
• Difficult   to   instill   sense   of   urgency   at   the   beginning   of  project
• More chance of team and customer turnover
• Break the project into smaller, shorter subprojects 
• Identify milestones to check that the project is on schedule
• Be diligent formal management procedures
• Rotate team members into different roles to keep up the interest level
• Strive to get ahead of schedule as early as possible. 
• Instill a sense of urgency from the start of the project
• Organize team-building activities to cohesion friction
• Ensure   all   major   deliverables   are   formally   approved,   so   that   change   management   can   be  invoked afterward
• Make   technical   design   and   architecture   decisions   as   flexible   as   possible   to   account   for  potential changes
Subject matter is well by the project team
• Longer learning curve for project team members
• The   project   may   slip   behind   in   the   early   portions   of   the  project
• sense for whether requirements sense
• Possibility that critical features or functions will be missed
• Need   to   initially   rely   on   customer   for   all   subject-matter  expertise
• Take as much training as practical, as early on as possible
• Bring the key customers onto the project team
• Spend extra time understanding and documenting the requirements
• Set approval process for requirements that require multiple subject-matter experts 
• Use   joint   application   design   (JAD)   session   to   gather   requirements   from   all   stakeholders  together
• Utilize more frequent walkthroughs and include the users
• Build extra time into estimates for application analysis and design activities









Guidelines for Project Risk Management
SW/G09/1.0.0 Internal 9 of 12

  Uncontrolled if copied/ printed
High on outside projects or teams
• in the other projects/teams could delay your project
• Changes   to   deliverable   from   other   projects/teams   could  force your project make changes
• More   complexity   involved   in   requirements,   design,   testing,  etc.
• More   chance   of   incompatible   standards,   processes,  technology
• More people and groups to with
• Harder   to   build   consensus,   longer   time   for   decisions   that  affect multiple groups
• Be very specific defining how other projects/teams affect your project
• Be very specific on the timing for when deliverables are from other projects/teams
• Establish central contacts as the focal points of communication between the projects/teams
• Include the dependent projects/ in reports and meetings
• communicate expectations from the other projects/teams
Business   processes   and   policies   require   substantial  change
• Policy changes could the project
• People   will   be   confused   with   new   processes,   which   will  affect their ability to utilize solution
• Possibility   that   new   processes   will   not   be   fully   integrated   at  first
• Possible   void   if   new   processes   don’t   fully   cover   all  contingencies
• System   functions   may   not   be   used   if   not   supported   by  correct procedures
• Substantial   change   in   processes   may   result   in   destructive  behavior
• Document all current policies and processes ensure that they are correct
• Communicate precisely how the new processes differ from the old ones
• Communicate potential changes as far in advance as possible
• Ensure the customers defining the policy changes
• Have one person responsible for all and policy changes
• Create an aggressive communication plan to keep customers engaged and informed
• Use   the   new   processes   in   a   pilot   test   or   prototype   first   to   ensure   they   are   workable   and  correct
• Include   the   successful   implementation   of   new   policies   and   processes   as   part   of   the  performance criteria for managers
• Be   open   to   customer   input   on   process   changes—for   better   ideas   and   to   allow   them   to   feel  they have impact
Changes to organization structure are substantial
• Organizational   uncertainty   can   cause   fear   in   the  organization
• People   may   not   focus   on   project   if   they   have   organizational  concerns
• People may fear loss of in a new organization
• People   may   not   use   the   system   if   they   are   unhappy   with   the  organizational change
• Uncertainty may cause decisions to be delayed
• Organizational   change   may   result   in   decisions   made   for  political purposes
• Document   the   concerns   that   come   out   of   a   new   organization   and   look   for   ways   to   mitigate  the concerns
• Communicate   early   and   often   about   the   potential   for   change   and   the   business   reasons   for  it
• Involve from all stakeholder areas in the organizational design and options
• human resources involved to deal with potential people issues









Guidelines for Project Risk Management
SW/G09/1.0.0 Internal Page 10 of 12

  Uncontrolled copied/ printed
The   project   technology   is   new   and   unfamiliar   (or   new  releases)
• Learning curve may result lower initial productivity
• May   be   integration   problems   between   old   and   new  technology
• Resistance   to   technology   changes   may   cause   the   project   to  be delayed
• May be difficulty testing the new technology
• Technology   may   not   be   installed   or   configured   correctly,  which will lead project delays
• New tools can lead to longer delivery times
• New technology may substantial efforts
• System   performance   may   be   poor   while   expertise   is   gained  in optimizing and the technology
• Provide much training on the new technology as practical, as as possible
• Train everyone who needs to install, use, or support the new technology
• Make arrangements to rely vendor technical specialists, when needed
• Use who familiar with the technology
• Make   sure   there   is   an   adequate   test   environment   where   the   technology   can   be   utilized  without affecting production
• Ensure   that   solid   analysis   is   completed   regarding   the   new   technology   functions,   features,  capabilities
• Create procedures and standards for the new technology should be utilized
• Create a test or prototype to utilize new technology in a small way at first
The   quality   of   current   data   is   poor   and   difficult   to  convert
• More work to the data to the new system
• Scrubbed may cause problems in the new system
• Data   conversion   problems   can   cause   significant   project  delays
• Make sure that all the old data elements are correctly mapped to the new system
• Test the conversion process rigorously before with conversion
• Determine   if   the   cost   and   trouble   associated   with   the   converted   data   is   worth   the   value.  Ask whether the new system start with new data only.
• the old system around for some period to the old data
• the effort to manually clean up old data as much as possible before conversion
Package implementation requires heavy customization
• Customization added to the project
• Making modifications may result in something else breaking
• Customization can lead to poor performance
• Customization can complicate migrating to newer releases
• Heavy   customization   may   mean   that   the   wrong   package  was selected
• Package will probably take longer to implement
• will more reliance on vendor
• Consider packages
• Consider custom development 
• Cut on the business requirements so that customizations are not required
• Get   a   firm   estimate   of   the   cost   and   duration   of   the   modifications   from   the   vendor   and   build  into your overall workplan
• Manage the vendor relationship to ensure all needed work is completed on schedule
• sure the sponsor approved the customizations being proposed
• Thoroughly test the modified package for functionality and performance
• a vendor log to track issues and milestones









Guidelines for Project Risk Management
SW/G09/1.0.0 Internal Page 11 of 12

  Uncontrolled if copied/ printed
Package implementation is a new product or release
• Greater of problems surfacing
• More   reliance   on   the   vendor   to   ensure   problems   are  corrected quickly
• Installation, testing, and deployment will take longer
• Hard   to   know   up   front   whether   the   package   meets   all   the  requirements
• Schedule training on the package early the project as possible
• an internal resource, or a consultant, with product experience onto the project
• Schedule   a   pilot   test   or   a   prototype   to   gain   familiarity   with   the   package   before   full  implementation
• Establish   agreements   with   the   vendor   stipulating   support   level   and   problem   resolution  times
• See if the project can be delayed until other companies have the product
• Seek out other companies have used the product for their feedback and key learning’s
Package implementation is from a vendor
• Possibility   that   vendor   may   not   survive   and   leave   you   with  no support
• Upgrades   may   be   in   jeopardy   if   there   are   not   enough   sales  in the marketplace
• No   prior   relationships   from   which   to   build   a   quick  partnership
• Legal   and   financial   concerns   may   delay   contracts   and   the  project
• Make sure that agreements with the vendor be in writing
• Insist that source code be placed escrow case does not survive
• the vendor to be a part of the project team
• Maintain a vendor log to track problems with the package
• Make sure the vendor financially sound
• Establish   agreements   with   the   vendor   stipulating   support   level   and   problem   resolution  times







Pls. refer to the guideline for preparation of PMP guideline for risk tracking.
< End of Document >
Project Risk Management
SW/G09/1.0.0 Internal Page 12 of 12

  Uncontrolled if copied/ printed